Proposed site in the Tees Valley

  • The proposed 6.5 hectare (ha) site is located approximately 2km to the south east of Billingham, Teesside. The site forms part of a petrochemical cluster and was previously occupied by a power station, which has since been demolished, leaving a flat undeveloped area.

  • The proposed plant includes fuel collection and storage facilities

  • The construction of the plant is expected to take approximately 24 months, with commissioning and testing taking a further 6 months

  • It is expected that the plant will operate initially for up to 25 years,  Following this the plant would be decommissioned and removed -  this is a straightforward operation after which the land will be made available for alternative uses.